Job Calendar
The primary method for scheduling Jobs in Deacomis handled via either the Job Calendar, Job Inventory Calendar, or Master Production Calendar (MPC). The Jobs and Jobs Inventory Calendars display a single box per Production Job and display the Job on a particular day on the calendar based on either the Job’s Planned Start date, Planned Finish date, or due date (original planned completion of job), depending on the selection made in the "Date Based On" field of the Calendar Selection pre-filter. Both calendars contain the same information, but the Job Inventory calendar uses color to display the inventory status of the Job. When allocating inventory to a Job on the calendar, the system will not allocate inventory that expires before the calendar date the Job is on. For information on setting up and using the calendar as well as how orders are displayed and scheduled, refer to the Scheduling Production Jobs Using the Job Calendar page.
General form layout
Once generated, the Job calendar form has three main sections.
-
Toolbar - Contains buttons to change the view of the calendar, save changes made, print and view schedules, etc. These items are detailed in the Job Calendar form section below.
-
List of Jobs available for scheduling - Including Job number, quantity, Facility, and Priority.
-
Jobs display according to the "Job Sort 1-3" pick list selections made in Production Options.
-
Jobs may be dragged and dropped to the desired date/time.
-
Double clicking a Job in this section will open the detail in view mode.
-
-
Calendar area used for scheduling - Days are listed, Monday-Sunday in either a weekly or monthly layout, depending on the "View" selected.
-
Listed under each date are details regarding the Job quantity scheduled and available units (calculated as the "Units Per Day" value on the Calendar Selection pre-filter minus the Job quantity). These values will update depending on the calendar view (for example, if the user clicks "Next Week") and when Jobs are dropped onto or removed from the calendar.
-
Orders scheduled on the calendar will block off a portion of the day. This "block" displays up to five lines of text, dictated by the "Job Field 1-5" pick list selections made in Production Options. The "Remaining" and "Finished" quantity fields available to the "Job Field 1-5" fields are useful to help properly schedule plant work on a daily basis.
-
The "Monthly Job Field 1-3" fields, available via Production Options, may be used to dictate the information displayed on the calendar when "View" is set to "Monthly".
-
Double clicking on a scheduled Job will open the Daily Job Calendar form, detailed in the Daily Job Calendar form section below.
-
System Navigation
-
Production > Calendar
Job Calendar form
Opened via the "View" button on the Calendar Selection pre-filter when the "Report Type" is set to "Jobs". The date used as the current date is displayed on the left side of the calendar.
Button |
Description |
---|---|
Previous 4 Weeks | Moves the view of the calendar to show the schedule for four weeks previous. |
Previous Week | Moves the view of the calendar to show the schedule for the previous week. |
Today | Moves the view of the calendar to show the schedule for the current day. |
Go To |
Opens a form that allows the user to jump to a particular date on the calendar. The fields are as follows:
|
Next Week | Moves the view of the calendar to show the schedule for the next week. |
Next 4 Weeks | Moves the view of the calendar to show the schedule for four weeks forward. |
View | Switches the view of the calendar between Monthly and Weekly, which allows users to get a picture of all Jobs scheduled. |
Save | Only available once at least one modification has been made to the schedule. If clicked, all modifications made are saved. |
Undo |
Reverts the previous modification made to the schedule.
|
Redo |
Undoes the reverted action previously performed via the "Undo" button.
|
Undo All | Reverts the schedule back to the way it was as of the last save. |
Refresh | Refreshes the data shown in the schedule. |
Opens the Print Schedule form, which allows users to print the schedule as is for a specified date frame.
|
|
Schedule | Opens the Daily Job Calendar form, which provides additional details regarding the orders displayed and the abilities to print, issue/de-issue, close a Job, run MRP, etc. |
Shop Schedule Basics | Opens the Availability list, which defines the schedule of available times for a Facility, Shop Area, or Work Center. |
Shop Schedule Exceptions | Opens the list of Availability Exceptions, which define any availability exceptions for a Facility, Shop Area, or Work Center based on the defined Shop Schedule Basics. |
Daily Job Calendar form
Opened via the "Schedule" button on the Job Calendar form or by double clicking a scheduled Job, the Daily Job Calendar form is a critical component of the DEACOM calendar functionality since it allows users to issue and de-issue materials to Jobs, modify Jobs, close Jobs, and print production documents such as picking lists and batch tickets. The "Job date 1-5" fields (jo_userdate1 thru jo_userdate5) and Work Center are available to this grid layout.
Button/Field |
Description |
---|---|
Previous Day | Moves the view of the form to show the Jobs scheduled for the previous day. |
Next Day | Moves the view of the form to show the Jobs scheduled for the next day. |
Modify | Opens the detail for the selected order in modify mode. |
View Detail | Opens the detail for the selected order in view mode. |
Opens the Copies to Print form, which allows the user to print various production Report Layouts. | |
Print Schedule | Opens the Print To form, which allows the user to print the current details. |
De-Issue | Opens the De-Issue/Un-Reserve Inventory form, which allows the user to de-issue any materials previously issued to the Job. |
Issue | Opens the Issue/Reserve Inventory form, which allows the user to issue materials to the Job. |
Inventory Detail | Opens the Calendar Color Detail form, which displays all Parts included on the Job(s) listed and their required and on hand amounts. This form also contains an "Availability" button, which runs basic item availability (displayed similarly to MRP) for the selected Part. |
Edit Data | Opens the Edit Calendar Job/Sale Data form, which allows the user to modify some details of the Job. |
Close Job | Opens the Close/Relieve Job form, which is used to relieve costs and materials, close Jobs, and print labels. |
Job MRP | Shows an MRP report for the Job selected. |
QC Values | Opens the Quality Control Results form, which displays any previous QC results that have been entered and is used to enter or change QC results, and/or approve, fail, and/or finish QC. |
Date | Displays the calendar date that is currently being viewed on the form. |
Display | Pick list used to display only Jobs that have not had any reports printed previously or all Jobs regardless of if reports were printed. |
Edit Calendar Job/Sale Data form
Opened via the "Edit Data" button on the Daily Job Calendar form. Security exists to control access to this form. If the security setting "Production -- Change planned job dates with scheduled routes" is set to true, users can override Planned Start and Planned Finish dates on a Job when setting it to manual.
Field |
Description |
---|---|
Job For |
The name of the customer linked to the Job.
|
Number | Displays the Job number. |
Shop Area |
Search field that displays the current Shop Area, if one is selected on the General tab of the Job, and allows the user to select a new one if necessary.
|
Freight | Search field that displays the current Freight Type, if one is selected on the Job, and allows the user to select a new one if necessary. |
Scheduled | The date for which the Job has been scheduled on the calendar. |
Delivery Time | Indicates the time that the Shop Area should have the necessary work completed. |
Priority |
Displays the Priority of the Job and allows the user to assign a new Priority if necessary.
|
Description | The Description as specified on the General tab of the Job. |
Planned Quantity | The Planned Quantity as specified on the Job. The value can be changed in this field and after saving the form will update the remaining amount of time. |
Planned Start |
The Planned Start date as indicated on the Dates tab of the Job, which indicates when production on the Job should start and may be modified if necessary.
|
Planned Finish |
The Planned Finish date as indicated on the Dates tab of the Job, which indicates when production on the Job should complete and may be modified if necessary.
|